Lessons Learned

Lessons Learned865


Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

PGNiG
4844 – PGNiG

Deepsea Yantai Marine
Own Experience
Operational 6608/1-1 S
Copernicus
Top hole 09/09/2022
Everything went according to plan and logging was done remotely. Final position report was delivered . . .

Stian Engvik / Morten Laget


PDF


Edit


PGNiG
4835 – PGNiG

Deepsea Yantai Drilling
Own Experience
Operational 6608/1-1 S
Copernicus
Surface section 04/09/2022
When the rig reached a TD of 1100 m and no contingency 4-string design was needed anymore, the 20″ . . .

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4840 – PGNiG

Deepsea Yantai Logistics
Own Experience
Operational 6608/1-1 S
Copernicus
Top hole 04/09/2022 With good planning and cooperation, everything shipped to SSJ prior to operation start in due time. . . .

Johan Kjos-Hanssen / Morten Laget



PDF


Edit


PGNiG
4841 – PGNiG

Deepsea Yantai Drilling
Own Experience
Operational 6608/1-1 S Intermediate section 04/09/2022 Had to switch to a BX elevator

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4830 – PGNiG

Deepsea Yantai Marine
Own Experience
Operational 6608/1-1 S
Copernicus
Rig move 29/08/2022 All tubulars were backloaded from the rig and mud and bulk tanks emptied. The rig was deballasted to . . .

Phil Hardy / Morten Laget


PDF


Edit


PGNiG
4831 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
29/08/2022 When the conductor was lowered to the seabed it was realised that a blanking plate from the Wellhead . . .

Phil Hardy / Morten Laget


PDF


Edit


Wellesley
3373 – Wellesley

Borgland Dolphin Marine
Own Experience
Operational 36/1-4
Hemispheres
Rig move 18/02/2022 Uncontrolled runout of anchor and chain

Stian Engvik / Morten Laget



PDF


Edit


Wellesley
3246 – Wellesley

Borgland Dolphin Drilling
Own Experience
Operational 36/1-4
Hemispheres
P&A 29/01/2022
Cement plug was pumped without incident, POOH through cement was without incident. Circulated clean . . .

Drilling Supervisor / Morten Laget



PDF


Edit


Wellesley
3241 – Wellesley

Borgland Dolphin HSEQ
Own Experience
Operational 36/1-4
Hemispheres
N/A 28/01/2022 There was a dropped object (DO) incident onboard BGL, and DO is not included in the reporting & . . .

Anniken Meisler / Morten Laget


PDF


Edit


Wellesley
2413 – Wellesley

Borgland Dolphin Drilling
Own Experience
Operational 36/1-4
Hemispheres
Surface section 04/01/2022
Ahead of a connection at 1146m (105m below the 13 3/8″ shoe), a blockage occurred in the cuttings . . .

Drilling Supervisor / Morten Laget


PDF


Edit


Wellesley
2409 – Wellesley

Borgland Dolphin Drilling
Own Experience
Operational 36/1-4
Hemispheres
Top hole 01/01/2022 When making up 18 3/4″ WHH to No Cross joint it was very tight clearance for upper and lower jaws to . . .

Drilling Supervisor / Morten Laget


PDF


Edit


Wellesley
2401 – Wellesley

Borgland Dolphin Drilling
Own Experience
Operational 36/1-4
Hemispheres
Production section 30/12/2021 ALL mud skips was put on the same boat, effectively removing any hope for recieving backload on said . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
2347 – Wellesley

Borgland Dolphin Logistics
Own Experience
Operational 36/1-4
Hemispheres
Top hole 28/12/2021
Saga Fjordbase took the 75ft riser joint and backloaded in addition to the 30″ conductor joints. The . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
2346 – Wellesley

Borgland Dolphin Logistics
Own Experience
Operational 36/1-4
Hemispheres
WELS/Kabal software 27/12/2021
Dolphin HR-personnel booked and moved people in WELS, then they confirmed them in WELS also, in . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
2326 – Wellesley

Borgland Dolphin Logistics
Own Experience
Operational 36/1-4
Hemispheres
Top hole 26/12/2021 The base and boat backloaded the primary and secondary 18 3/4″ WHHs instead of two 30″ conductor . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
2323 – Wellesley

Borgland Dolphin Drilling Operational 36/1-4
Hemispheres
Top hole 24/12/2021 Tool used successfully but Schlumberger should be told what our requirements are at the planning . . .

Drilling Supervisor / Morten Laget


PDF


Edit


Wellesley
2324 – Wellesley

Borgland Dolphin Drilling
Own Experience
Operational 36/1-4
Hemispheres
Top hole 24/12/2021
30″ conductor and cement was cleaned out with seawater and sweeps, hole displaced to 1.40 SG . . .

Drilling Supervisor / Morten Laget


PDF


Edit


Wellesley
2325 – Wellesley

Borgland Dolphin Drilling
Own Experience
Operational 36/1-4
Hemispheres
Top hole 24/12/2021
The deck-crew on days started to lay out slick joints in one bay before a crew change happened in . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
2321 – Wellesley

Borgland Dolphin Drilling
Own Experience
Operational 36/1-4
Hemispheres
Top hole 23/12/2021 o At 281m conductor couldn’t pass due to the tight spot observed when drilling there. Attempted to . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
2322 – Wellesley

Borgland Dolphin Logistics
Own Experience
Operational 36/1-4
Hemispheres
Top hole 23/12/2021
It was observed in the manifest that the connection on the 13 3/8″ swages was Vam21, in addition to . . .

Drilling Engineer / Morten Laget


PDF


Edit